PROCESSING THIRD PARTY PLANT ENQUIRY REQUESTS AND NETWORK PLANT PROTECTION

CLIENT

Tata Communications, KPN International, CGI and Sota

CHALLENGE

• To provide a robust plant protection process safeguarding our clients ‘network assets from damage by proposed third party works

SOLUTION

• Check third party plant enquiries against client as built network mapping database
• Classify plant enquiries into affected and not affected categories and log on to the database
• Reply to all third party plant enquiry requests confirming whether our client’s network is affected
• Where the client’s network is affected, provide copies of as built drawings to the third party

RESULTS AND BENEFITS

• Responses all third party plant enquires produced in line with NRSWA 1991 guidelines and timetable
• Clients are reassured that their networks are protected
• Monthly reports to clients of all processed plant enquiries keep them up to date

SOME NUMBERS

58593

Plant  enquiries processed

81

Highway section defects resolved

879

Careline enquiries processed

5545

Stats packs issued